Build Frequently Asked Questions

RHDC 24 Bxall July 2019

12 August 2019

Update from Baxall Construction

We are progressing well, considering the challenging weather conditions. We currently have the last of the external walls being installed by Inwood, with the roof cassettes (pre-manufactured panels) being delivered today and tomorrow. So, with good progress (weather permitting), we should have all of the roof installed this week. 

(Inwood is the company supplying the timber frame building and Sweet Chestnut cladding for the Rye Harbour Discovery Centre, under construction by Baxall. Interview with Inwood Director Nigel Barden here)

Once we have the roof installed we will then begin installing the 'vapour barrier' to get the building water tight as quickly as possible. Once we have installed the roof, we will also begin mechanical and electrical 'first fix' works internally. (Link to Wiki page about what 'first' and 'second' fixes mean, in general)

Why are you using concrete and steel?

A building of this type and dimensions, built on a shingle substrate, needs robust foundations. The architect's advice is that this is best achieved with a concrete base supported by piles. We are seeking to make the building as environmentally sustainable as possible, with the chestnut cladding and use of natural light and ventilation. The Discovery Centre is being made using locally sourced, Sweet Chestnut cladding. The design includes photovoltaic panels covering half the roof. The building and surrounding landscaping will provide many places for wild plants and animals to live. The ventilation will be passive and the heating will utilise air sourced heat pumps.

Is the building process affecting access to the reserve?

The reserve is remaining open for the whole of the build, but there is a diverted route of a two metre wide, pedestrian walkway at the same height as the road, on the right hand side of the road as you go towards the sea. This still provides access for wheelchairs, buggies and bicycles. Hoardings alongside the building site display information for visitors.

Where are Baxall staff and equipment based?

There is an enclosed section of the carpark fenced off where their portacabins are based for the duration of the build. They need to be near services such as electricity. The Coastguard have been really helpful, allowing Baxall to connect to their services, and we also appreciate the support of Icklesham Parish Council

Walkway RHDC (c) Emma Chaplin 

Will there be much noise and disruption?

Large scale movements of vehicles will be minimised, but there will inevitably be more traffic than at present. 

Won't it disturb the birds?

They are coping very well. They quickly learn to adapt and tolerate noises once they've heard them a few times.

When will the work finish?

The build should take 38 weeks. Baxall hope to finish by the end of January 2020, ready for the official opening in March 2020 to coincide with the 50th anniversary of the reserve, but we will continue to issue updates.

What’s happening to waste material? Will building materials get blown about if it’s windy?

Baxall will be removing waste material from site regularly, and they are aware of the geographical challenges of Rye Harbour Nature Reserve, so will be taking great care. Material from the site will be transported to a registered waste recycling centre.

Will the village drainage system be able to cope?

The building will be connected to the main sewer, with a strategy that has been agreed with Southern Water. 

Is there any overnight security?

Access through the site is now closed to all traffic. Additional warning signs have been installed onto the main security gate and site fencing.

The site is also covered by CCTV cameras that are observed 24/7.

Photography

There will be timelapse photography and other means of recording the build process. Any use of drones will have been approved by the Reserve Manager.

Why is the Discovery Centre being built?

At the moment, we don’t have adequate facilities for the large numbers of annual visitors we welcome on the reserve, including parties of schoolchildren. The same is true for staff and volunteers. The nature reserve is vast, and it needs somewhere accessible, that offers shelter in all weathers, and has facilities including toilets, all of which enable everyone to enjoy our reserve, all year round.

Won't having a visitor centre cause problems with traffic and parking?

Parking for the reserve will be directed to the existing car parks in Rye Harbour, Rye and Winchelsea Beach. The brown tourism signs direct people to Rye Harbour. The car park and toilets there are run by Icklesham Parish Council. There would be potential greater capacity in the car park if it was white lined. We appreciate that at peak times there are too many cars for the parking spaces available in all of Rother District and we are working with the Sussex Community Rail Partnership to promote visiting by rail on our website and in our literature.

How can we get more information?

Information Centre volunteers are getting regular updates from Senior Site Manager Matt Fothergill.

You can sign up for monthly e-news, follow us on Twitter @RyeHarbour_NR, follow the project on Baxall’s Twitter @Baxall_RyeHarbourDiscovery, and keep an eye on this website ryeharbourdiscoverycentre.org.uk

The email address for Baxall for this project is ryeharbour@baxallconstruction.co.uk

The email address for the Rye Harbour Nature Reserve staff team is RHNRoffice@sussexwt.org.uk

Smaller RHNR (c) Stuart Conway drone photo  discovery centre site apr 2019 

Thanks to Stuart Conway for the drone photo of the site, taken April 2019 www.stuartconway.com